08/02 February Update

Villa Update

Mead have completed the brick and blockwork for the Villa as well as the roof structure. The clay roof tiles have been installed, with the windows due for installation mid-Feb.

Penthouse Update

The roof area in all 3 blocks is being cleared, to enable the removal at the end of February 2024. Due to the large deliveries scheduled for the month of April, parking spaces parallel to Parson Street will be suspended. The parking spaces in front of the Villa will be retuned, and available for us from March 2024.

Communal Works

The communal works have been rescheduled to commence in April 2024 and complete in July 2024. The existing lift will be decomissioned from April 2024. Thereafter, the communal refurbishment works can commence including the replacement of the communal flooring, wall repainting, new communal doors and new electrical lighting.

Programme:

Mead are currently 2 months behind programme, meaning the Main Works are due to complete in September 2024. The below dates are indicative and may be subject to movement.

  • Villa Completion: May 2024

  • Lift Downtime: April 2024 - July 2024

  • Communal Redecoration: April 2024- July 2024

  • Penthouse Completion: September 2024

The next website update will be on the 22nd of February 2024.


Previous
Previous

05/04 April Update

Next
Next

12/01 January Update