14/09 September Update

Letter to residents from Mead Building Contractors regarding the construction works at Mulberry Close. To read please click here.

The Villa superstructure works will commence shortly, alongside the Penthouse enabling works (including scaffold erection).

The parking area in front of the Villa will remain cornered off for another few weeks, until such a time as the drainage is fully complete.

Please see below key target dates:

  • Villa Completion: March 2024

  • Install Penthouse scaffold towers: September and October 2023

  • Lift Downtime: Between December 2023- April 2024

  • Communal Redecoration: February 2024- April 2023

  • Penthouse Completion: August 2024

The next website update will be on the 28th of September.